Fabric Inspection Checklist: Printable, Stage by Stage
A printable fabric inspection checklist for mills and garment exporters: receiving, set-up, 4-point inspection, checks, relaxation and release to cutting.
By Radiatus team · Published 04 Nov 2026 · Updated 04 Nov 2026 · 8 min read
A fabric inspection checklist is the list of checks a QC team runs on every lot of fabric from the moment it arrives to the moment it goes to the cutting table, with who does each check, which record proves it was done and what counts as a pass. This printable fabric inspection checklist is organised in five stages, the order in which the work actually happens on an Indian mill or garment-export floor, and ends with knit and woven add-ons. It is a checklist, not a procedure: for the full written method, see our fabric inspection procedure and SOP template.
What should a fabric inspection checklist cover?
Most checklists found online are a list of defects to look for. That is the middle of the job. A complete fabric inspection sheet also covers what happens before the frame (is this the fabric we ordered, in the quantity we were invoiced?) and after it (is the roll graded, labelled, relaxed and released with evidence?). Each item below has three parts:
- Who does it: store, inspector, QC head or cutting.
- The record that proves it: a ticket, a reading, a photo, a signature or an app entry.
- The pass rule: almost always the buyer's own figure, never a number the inspector remembers.
Paper checklists fail at the record part. A tick says the check was done, not what was found. Wherever you can, write the value, not just the tick.
Stage 1: receiving
Before a single roll goes on the frame, match the delivery to the paperwork. Most length and weight disputes with mills are lost at this stage because nobody wrote the ticket figures down before the rolls were opened.
| Check | Who | Record | Pass rule |
|---|---|---|---|
| Packing list matches the PO: fabric, colour, GSM, width, roll count | Store | Packing list stamped with the PO number | Matches the PO |
| Each roll has a ticket: roll number, lot / dye lot, length or weight | Store | Ticket values entered per roll | Every roll identified |
| Weigh knit rolls bought by the kg; subtract tube and polybag | Store | Scale reading, tare, net kg | Net kg within the buyer's or mill's weight tolerance |
| Transit damage, wet or soiled rolls, crushed tubes | Store | Photo per damaged roll | None, or noted on the delivery challan |
| Moisture or smell on cotton rolls (stored damp) | Store | Note on the roll | None |
For knit rolls, the net weight also tells you roughly how long the roll should be. Our kg to meter fabric calculator converts weight to metres and yards from GSM and width, with tube width and tare.
Stage 2: set-up
The same inspector on the same frame will give different results under poor light or at a different speed. Fix the conditions, write them down and keep them the same for the whole lot.
| Check | Who | Record | Pass rule |
|---|---|---|---|
| Lighting at the frame as the buyer manual specifies; lamps working | QC head | Light check in the shift log | As per buyer manual |
| Frame speed set to the factory's chosen setting for this fabric | Inspector | Speed noted on the sheet | Same setting for the whole lot |
| Correct buyer standard picked: scoring system, roll limit, hole rule | QC head | Buyer and standard on the roll record | Matches the order |
| Sampling plan applied: which rolls to inspect | QC head | Sample list for the lot | Buyer plan, e.g. 10 % per colour or ISO 2859-1 |
| Approved shade swatch and GSM cutter at the frame | Inspector | — | Available before starting |
Stage 3: during inspection
This is the part every checklist has, but the detail matters. Under the 4-point system (ASTM D5430) each defect gets 1 to 4 points by length, holes follow the buyer's hole rule, and no linear yard carries more than 4 points.
| Check | Who | Record | Pass rule |
|---|---|---|---|
| Every visible defect logged with type, points and yard position | Inspector | Defect log or roll map | Points by the buyer's scoring system |
| 4-points-per-yard cap applied | Inspector | Points per yard | Never more than 4 in one linear yard |
| Running defects (needle lines, barre, creases) logged with start and length | Inspector | Start yard and run length | 4 points per yard; buyer's reject length |
| Photo of every major defect (3–4 points) and every hole | Inspector | Photos linked to the defect | Evidence for claims |
| Width at start, middle and end | Inspector | Three width readings | Within the buyer's width tolerance |
| Shade side-centre-side and against the swatch | Inspector | Shade note or reading | Within the buyer's shade band |
If you score by hand, check the arithmetic with the free 4-point system calculator: points × 3600 ÷ (yards × width in inches).
Stage 4: after inspection
| Check | Who | Record | Pass rule |
|---|---|---|---|
| Points per 100 sq yd calculated and compared with the roll limit | Inspector | Result on the roll | At or below the buyer limit |
| Measured length against the ticket length | Inspector | Measured and ticket length | Shortage within the buyer's tolerance |
| Bow and skew measured (ASTM D3882) | Inspector | Distance and width, % | Within the buyer's % |
| GSM from a cutter sample | Inspector | GSM value | Within the buyer's GSM tolerance |
| Shrinkage test where the buyer asks for it | Lab / QC | Warp and weft % | Within the buyer's range |
| Roll graded (first / second / reject) and labelled | QC head | Grade and label | Label on every roll |
| Failed or short rolls held and claimed | QC head | Hold tag, debit note | No failed roll goes to cutting by mistake |
For how to measure and calculate shrinkage, see our guide to the fabric shrinkage test method and formula.
Stage 5: before cutting
| Check | Who | Record | Pass rule |
|---|---|---|---|
| Relaxation started for knits and stretch fabrics, with a card | Store | Start time, hours, rack | Hours from the buyer manual or chart |
| Relaxation time completed before issue | Store / cutting | Issue time | No early release without a recorded approval |
| Shade bands grouped so one garment never mixes bands | QC head | Shade band per roll | Bands kept apart in the lay |
| Released rolls signed off to cutting | QC head / cutting | Release signature, cut number | Only passed, relaxed rolls |
How long to relax which fabric, and what to record, is covered on our page about fabric relaxation: time chart, SOP and report format.
Knit and woven add-ons
For knits, add: net weight against the ticket weight for every roll; tubular or open width written on the report (dividing by the tube width doubles the points); lycra out, needle lines, press-off and holes in the quick defect list; spirality after washing where the buyer asks; relaxation before cutting as a hard stop, especially for spandex blends.
For wovens, add: bow and skew on every inspected roll; selvedge defects and width at three points; warp and weft direction on each defect where the buyer uses the 10-point system; shade side-centre-side on wide sheeting; and the buyer's running-defect reject length for stripes and reed marks.
Printable fabric inspection checklist
The five stage tables above, printed together, are the printable checklist. Use your browser's print function (Ctrl+P on a computer, Share → Print on an Android tablet) and choose "Save as PDF" to get a fabric inspection checklist PDF for your floor. Put the QC head's name and the date at the top of each copy, and file one per lot with the inspection report. A checklist that is not filed with the lot it describes is not evidence.
From checklist to records: how the app captures each item
Every item in this checklist has a place in Fabric Inspection Software, so a tick becomes a value with a time and a name. Rolls are registered with ticket length or weight at receiving; knit rolls are weighed against the ticket and the length worked out from GSM and width. The buyer standard carries the scoring system, limits, hole rule, tolerances and sampling plan. Inspectors log defects by tap or voice with photos on a ₹10,000 Android tablet, offline if needed, and the app applies the per-yard cap and computes points per 100 sq yd live. Width, length, bow, skew, shade, GSM and shrinkage sit on the same roll. Relaxation is timed on a board that will not release a roll to cutting early, and every failed or short roll drafts a debit note to the mill. See how the fabric inspection app works or the plans from ₹4,999 a month on the pricing page.
Questions people ask
What is checked during fabric inspection?
Visible defects scored under the buyer's system (usually the 4-point system per ASTM D5430), width at three points, length against the ticket, shade against the swatch and side to side, and, after the frame, bow and skew, GSM and shrinkage where required. Each roll is then graded, labelled and held or claimed if it fails.
Is there a fabric inspection checklist PDF?
Yes: print this guide from your browser and choose Save as PDF. The five stage tables (receiving, set-up, inspection, after inspection, before cutting) form a complete printable checklist with who, record and pass rule for each item. File one completed copy per lot with the inspection report.
What is the difference between a fabric inspection checklist and a report?
The checklist lists the checks to run and proves they were done; the report gives the results for each roll: defects, points per 100 sq yd, verdict, measurements and photos. A buyer usually receives the report; the checklist stays in the factory as evidence that the procedure was followed.
How many rolls should be inspected per lot?
As many as the buyer's sampling plan says. A common convention is at least 10 % of rolls per colour, width and construction, rising to 100 % when the previous lot failed; some buyers use ISO 2859-1 sample sizes or the square root of the roll count. Write the plan used on the checklist.
Who signs the fabric inspection checklist?
The inspector signs the stages they performed and the QC head signs the grading and the release to cutting. The store in-charge signs receiving and relaxation. Signatures matter less than names with times; Fabric Inspection Software stamps every entry with the user and time automatically.
Can the checklist be filled on a tablet?
Yes. Fabric Inspection Software turns each checklist item into a record on an Android tablet: ticket and weight at receiving, defects with photos during inspection, width, bow, skew, GSM and shrinkage afterwards, and the relaxation board before cutting. Tap logging keeps working offline and syncs when the network returns.
Related guides
Fabric Inspection Procedure: SOP Template and Flow Chart
A fabric inspection procedure to adopt as your SOP: scope, roles, sampling, set-up, 4-point grading, records and a flow chart from receipt to cutting.
Fabric Reconciliation in Garment Industry: Report Format
How to reconcile fabric per PO in a garment factory: received, short, rejected, issued to cutting, end bits and balance, with a worked example and format.